Skip to content
Liquefied natural gas

Yamal LNG, Russia

Please check an answer for every question.
Cookie settings

Total may deposit the following categories of cookies: Cookies for statistics, targeted advertising and social networks. You have the possibility to disable these cookies, these settings will only be valid on the browser you are currently using.

Enabling this cookie category allows you to establish statistics of traffic on the site. Disabling them prevents us from monitoring and improving the quality of our services.
Our website may contain sharing buttons to social networks that allow you to share our content on these social networks. When you use these sharing buttons, a link is made to the servers of these social networks and a third-party cookie is installed after obtaining your consent.
Enabling this cookie category would allow our partners to display more relevant ads based on your browsing and customer profile. This choice has no impact on the volume of advertising.

With 500,000 tons of modules, four 160,000-cubic-meter storage tanks, an export terminal that has two loading docks, cryogenic pipelines with diameters of up to 1.2 meters, and massive rotating machinery, Yamal LNG was a colossal project to build. Faced with such complexity during the commissioning phase, our dedicated teams applied an extremely rigorous methodology that enabled production to start up less than one year later.

The numerous objectives of the commissioning phase include ensuring equipment safety, handing over to operations teams on schedule, optimizing the project’s efficiency and profitability, and maintaining written records of each stage in the process.

To achieve all of these objectives, Total adopts an overarching approach that enables us to take into account any interaction with, or impact on, other aspects of the project.

All of the inspection and control procedures required for each operating component are defined in the overall methodology, ensuring the best possible conditions for a safe, secure and on-schedule start-up.

Four commissioning areas were defined for the Yamal LNG project — the condensate pre-processing and storage facilities, the LNG trains (utilities and offsites), the LNG tanks, and the main power generation units.

In Phase 1 alone, construction and pre-commissioning teams filled out some 800,000 forms and commissioning teams, around 100,000.

In all, 1,400 subsystems were tested and 2,400 scenarios controlled, requiring commissioning and start-up to be carried out as simultaneous operations (SIMOPS).

yamal_map_exploration_production_total

 

0
million metric tons are annually produced on Yamal LNG
0
m3
the storage capacity of our LNG ice-breaker
0
operators working on site at the peak of construction

Yamal, Russie

Our commissioning standards in extreme circumstances: the superlative project in the Yamal peninsula

  • Operators on the construction site of the Yamal project, Russia - Exploration-Production - Total
    Operators on the construction site of the Yamal project, Russia
  • Yamal LNG plant dockyard, Russia - Exploration & Production - Total
    Yamal LNG plant dockyard, Russia
  • Yamal LNG plant, Russia - Exploration & Production - Total
    Yamal LNG plant, Russia
  • Christophe de Margerie LNG tanker on the Kara Sea, Russia - Exploration-Production - Total
    Christophe de Margerie LNG tanker on the Kara Sea, Russia
  • Yamal LNG plant at dusk, Russia - Exploration & Production - Total
    Overview of the Yamal LNG plant at dusk, Russia
Operator at Yamal LNG in Russia - Exploration Production - Total

Total in Russia

Explore the website of our Russian operations

Total Group

Get to know Total: a major energy operator

LNG, an Energy for the Future

Liquefied Natural Gas development is a key element of the Group's strategy
Christophe de Margerie gas tanker at the port of Sabetta, Russia - Exploration Production - Total

Design an LNG ice-breaker ship

A new type of ship for LNG to be transported efficiently and at a steady pace